Sciweavers
Explore
Publications
Books
Software
Tutorials
Presentations
Lectures Notes
Datasets
Labs
Conferences
Community
Upcoming
Conferences
Top Ranked Papers
Most Viewed Conferences
Conferences by Acronym
Conferences by Subject
Conferences by Year
Tools
PDF Tools
Image Tools
Text Tools
OCR Tools
Symbol and Emoji Tools
On-screen Keyboard
Latex Math Equation to Image
Smart IPA Phonetic Keyboard
Community
Sciweavers
About
Terms of Use
Privacy Policy
Cookies
Free Online Productivity Tools
i2Speak
i2Symbol
i2OCR
iTex2Img
iWeb2Print
iWeb2Shot
i2Type
iPdf2Split
iPdf2Merge
i2Bopomofo
i2Arabic
i2Style
i2Image
i2PDF
iLatex2Rtf
Sci2ools
106
Voted
WSC
2007
85
views
Modeling And Simulation
»
more
WSC 2007
»
Optimal work breaks in deterministic and probabilistic repetitive projects
15 years 5 months ago
Download
www.informs-sim.org
An effective way to reduce the duration and cost of projects with repetitive activities is through the relaxation of
Photios G. Ioannou, Chachrist Srisuwanrat
Real-time Traffic
Effective Way
|
Modeling And Simulation
|
Repetitive Activities
|
WSC 2007
|
claim paper
Related Content
»
Simulation and optimization for construction repetitive projects using promodel and simrun...
more »
Post Info
More Details (n/a)
Added
02 Oct 2010
Updated
02 Oct 2010
Type
Conference
Year
2007
Where
WSC
Authors
Photios G. Ioannou, Chachrist Srisuwanrat