The single machine scheduling problem with sum of completion times criterion (SS) can be solved easily by the Shortest Processing Time (SPT) rule. In the case of significant uncertainty of the processing times, a robustness approach is appropriate. In this paper, we show that the robust version of the (SS) problem is NPcomplete even for very restricted cases. We present an algorithm for finding optimal solutions for the robust (SS) problem using dynamic programming. We also provide two polynomial time heuristics and demonstrate their effectiveness.